Work Resources Multi-Period

Internal Table Name: WorkResources_MultiPeriod

Period Name

Technology: NO IO S

Table: WorkResources_MultiPeriod

Internal Name: PeriodName

Type: Short Text (50)

Select the time period in which the changes to the work resource will occur.

Site

Technology: NO IO S

Table: WorkResources_MultiPeriod

Internal Name: SiteName

Type: Short Text (100)

Specify the site where this resource is used during this period.

Name

Technology: NO IO S

Table: WorkResources_MultiPeriod

Internal Name: WorkResourceName

Type: Short Text (100)

Select the name for the work resource which will change during this time period.

Units

Technology: NO IO S

Table: WorkResources_MultiPeriod

Internal Name: Units

Type: Short Text (25)

Enter the number of identical units of this resource available to perform work during this time period. It must be a whole number.

Fixed Resource Cost

Technology: NO IO S

Table: WorkResources_MultiPeriod

Internal Name: UnitFixedCost

Type: Short Text (50)

Enter the fixed unit cost for each work resource during this period. This is the fixed cost of a work resource, such as the general/administrative costs per worker for the period.

Hourly Cost

Technology: NO

Table: WorkResources_MultiPeriod

Internal Name: HourlyCostCap

Type: Short Text (50)

Specify the cost per hour for this resource during this period. You can also define a step function when cost varies by step level.

Maximum Capacity (Hours)

Technology: S

Table: WorkResources_MultiPeriod

Internal Name: WorkResourceMaxAvailableTimeinHours

Type: Number (Float)

Enter the maximum time (in hours) that each work resource can be utilized during this period.

Notes

Technology: NO IO S

Table: WorkResources_MultiPeriod

Internal Name: WorkCenterPeriodNotes

Type: Memo

Enter optional descriptive notes about the work resource.