Production Process Flows

Internal Table Name: OptimizationOutputProductionProcessFlows

This output table summarizes the specifics of all production process flows in the network.

Scenario

Table: OptimizationOutputProductionProcessFlows

Internal Name: Not Applicable (Scenario column not in table)

The scenario for which the summary data was generated.

Period Name

Table: OptimizationOutputProductionProcessFlows

Internal Name: PeriodName

The period in which this flow occurs.

Site Name

Table: OptimizationOutputProductionProcessFlows

Internal Name: SiteName

The site at which the process occurred.

Product Name

Table: OptimizationOutputProductionProcessFlows

Internal Name: ProductName

The name of the product being produced.

Process Type

The type of process used with the production process for this flow

Process Name

Table: OptimizationOutputProductionProcessFlows

Internal Name: ProcessType

The name of the process.

Process Step Name

Table: OptimizationOutputProductionProcessFlows

Internal Name: ProcessStepName

The name of this process step.

Next Process Step Name

Table: OptimizationOutputProductionProcessFlows

Internal Name: NextProcessStepName

The process step that occurs after the Process Step Name.

Work Center Name

Table: OptimizationOutputProductionProcessFlows

Internal Name: WorkCenterName

The name of the work center, if applicable, used by the process.

Work Resource Name

Table: OptimizationOutputProductionProcessFlows

Internal Name: WorkResourceName

The name of the work resource, if applicable, used by the process.

Flow Units

Table: OptimizationOutputProductionProcessFlows

Internal Name: FlowUnits

The number of units handled in this process flow.

Flow Weight

Table: OptimizationOutputProductionProcessFlows

Internal Name: FlowWeight

The weight of all units handled in this process flow.

Flow Cubic

Table: OptimizationOutputProductionProcessFlows

Internal Name: FlowCubic

The cubic size of all units handled in this process flow.

Flow Cost

Table: OptimizationOutputProductionProcessFlows

Internal Name: FlowCost

The total cost involved this flow.

flow cost = total number of flow units * unit process cost

Setup Cost

Table: OptimizationOutputProductionProcessFlows

Internal Name: SetupCost

The total cost involved in setting up this process.

setup cost = (total number of flow units * setup cost from Process Steps table) / lot size

Total Cost

Table: OptimizationOutputProductionProcessFlows

Internal Name: TotalCost

The total cost incurred for the production process flows of the product at the site in the specified period.

Process Time

Table: OptimizationOutputProductionProcessFlows

Internal Name: ProcessTime

This is the time incurred when work centers are utilized for the production process flows of the product at the site in the specified period.

Changeover Time

Table: OptimizationOutputProductionProcessFlows

Internal Name: ChangeoverTime

The time incurred during work center changeovers required for the process.

Work Resource Time

Table: OptimizationOutputProductionProcessFlows

Internal Name: WorkResourceTime

The time incurred in hours when work resources are utilized.

Period No

Table: OptimizationOutputProductionProcessFlows

Internal Name: PeriodNo

The sequence number for the period. This value is useful in sorting periods sequentially rather than by name.

Scenario ID

Table: OptimizationOutputProductionProcessFlows

Internal Name: ScenarioID

The identifier of the scenario for which the summary data was generated.

Sub-Scenario ID

Table: OptimizationOutputProductionProcessFlows

Internal Name: StepNumber

The identifier of the sub-scenario, if applicable, for which the summary data was generated.

Last modified: Wednesday May 15, 2024

Is this useful?